More from our record
Our record continues through hotels, condominium towers and public buildings.
Each entry states the scope documented for that property and phase.
PropertyBuildingOur documented work
Ritz-Carlton Amelia Island
Fernandina Beach, FL
8 stories · 448 units · Sovent
We accessed, inspected, cleaned and reinspected 40 sanitary risers in the phase completed in March 2015.
Tampa condominium towers
Tampa, FL
Two 30-story towers · 255 units
We camera-inspected and mechanically cleaned 16 Sovent risers and their base pressure-relief lines, collecting the debris with an industrial vacuum.
Riva Del Lago
Fort Myers, FL
Two 22-story towers
We reviewed the blueprints, inspected the pipes and set a work plan, then cleaned and reinspected ten kitchen and bathroom Sovent stacks. The customer's May 2015 letter reports the stacks were cleaned in two weeks and the work was examined by W.J. Johnson Engineering.
Vinoy Place
St. Petersburg, FL
Four 13-story towers
We cleaned and reinspected 44 kitchen, bathroom and laundry risers across the four towers.
Sancerre Condominium
Naples, FL · July 2014
9 stories · 23 units · Sovent
We inspected, cleaned and reinspected 38 sanitary risers, then cleaned and lined the overhead first-floor garage piping down to the slab.
Marbella Condominium
Naples, FL · August 2014
21 stories · 118 units · Sovent
We inspected, cleaned and reinspected six kitchen risers, then cleaned and lined the overhead first-floor main.
Ritz-Carlton Tysons Corner
McLean, VA · November 2015
24 stories · Sovent
We accessed, inspected, cleaned and reinspected three sanitary risers in the November 2015 phase.